Project Location ¶

Project falls within City Council District 4 & 6
Project Description
City Project No: 1001849; FPN 443711-2
This project provides for the design and construction of a new traffic signal based on a safety-related traffic warrant study.
Two new mast arm traffic signals at the intersection of W Cleveland Street and S Rome Avenue will be constructed and additional minor geometric changes will be made as appropriate. Improvements include curb bulb-outs, new crosswalks, pedestrian signals, ADA-compliant ramps, detectable warning mats, and drainage modifications.
New signals will reduce severe right-angle traffic crashes and provide better transportation network connectivity for all modes.
Contact Information ¶
Project Manager: Jae-Sang Lee
If you have questions about this meeting or project, please use the email link below:
Costs and Schedule ¶
Phase | Firm | Cost | Funding Source | Schedule Start | Schedule Finish |
---|---|---|---|---|---|
Design | Faller Davis & Associates | $121,000 | City | Mar-21 | Mar-22 |
Construction | TBD | $410,000 | FDOT/City | Oct-22 | May-23 |
Additional Information ¶

Figure 1 - Project Plans