Floribraska Ave Complete Streets Project (Tampa St to 9th St)

Project Location

Map of project location.

Project falls within City Council District 5

Project Description

City Project No: 1001531; FPN 436640-1

This project provides for multimodal and safety improvements including a cycle track and sidewalks.

This project reconfigures the existing 4-lane undivided roadway to a complete street with two (2) 10-feet travel lanes separated by a two-way left-turn center lane plus an on-road bidirectional cycle track, with a raised separator on the southern side of the road. The proposed improvements also include wider sidewalks, raised pedestrian refuge islands, and crosswalks at the intersections of both Jefferson St. and Central Ave.

Currently, the 0.6-mile segment of Floribraska Avenue between N. Tampa Street and 9th Street is an east-west, 4-lanes (two travel lanes in each direction) arterial roadway and bus route with a posted speed of 30 mph with an average daily traffic volume of 9,000 vehicles per day. The proposed improvements will reduce conflicts and sight obstruction hazards along the corridor making it safer for all users in accordance with the City’s Vision Zero initiative while maintaining the existing roadway’s level of service.

Contact Information

Project Manager: Nina Mabilleau, E. I.

If you have questions about this meeting or project, please use the email link below:

Costs and Schedule

Table 1 - Summary of Project Costs and Schedule
Phase Firm Cost Funding Source Schedule Start Schedule Finish
Design City / Stantec /Tony Monk $150,000 City CE Impact Fee Nov-19 May-21
Construction TBD $664,000 FDOT (LAP) Apr-22 Apr-23
Construction TBD $2,853,000 City CE Impact Fee Apr-22 Apr-23
Construction Inspection In-House $127,650 FDOT (LAP)+ City CE Impact Fee Apr-22 Apr-23

Additional Information


Updated: 05/17/2022