Gray St Bike Blvd. (West Shore Blvd to Rome Ave)

Project Location

Project Overview

This project provides for complete street roadway improvements to enhance safety and multimodal connectivity, including roundabouts, sidewalks, bicycle facilities, enhanced crosswalks and other safety measures.

This project evaluates complete street improvements along Gray St from West Shore Blvd to Willow Ave and will develop a bicycle boulevard as well improve pedestrian facilities throughout the corridor.

How to get involved:

Your comments are valuable to us and we want you to get involved!  Please use the tools below to provide your input.

  1. Send Email Comments to the Project Manager, Jorge Uy, P.E., PTOE, RSP-1

    Jorge.Uy@tampagov.net

Costs and Schedule

Table 1 - Summary of Project Costs and Schedule
Phase Firm Cost Funding Source Schedule Start Schedule Finish
Concept Study Landis Evans & Partners $49,000 Complete Streets Jan-21 Jun-21
Design Landis Evans & Partners $100,000 Complete Streets Sep-21 Mar-22
Construction TBD $500,000 Local Option Gas Tax TBD TBD

Additional Information

Figure 1 - Posted sign for full use of lane by cyclists

Figure 1 - Posted sign for full use of lane by cyclists

Figure 2 - Shared Lane Pavement Markings

Figure 2 - Shared Lane Pavement Markings