Rocky Point Dr - Complete Streets Improvements

Project Location

Map of project location.

Project falls within City Council District 6

Project Description

This project provides for safety and multimodal improvements.

The City proposes to mill and resurface as well as correct areas of ponding stormwater along Rocky Point Drive from the Courtney Campbell Causeway to the south end extent for an approximate length of 1,900 feet. The City also proposes to add a sidewalk on the west side from Bay Club Circle to the Courtney Campbell Causeway. 

Contact Information

Project Manager: Jola Olbinska, P. E.

If you have questions about this meeting or project, please use the email link below:

Costs and Schedule

Table 1 - Summary of Project Costs and Schedule
Phase Firm Cost Funding Source Start Finish
Design Pennoni $ 95,424 Complete Streets 2020 2022
Right-of-Way N/A N/A N/A - -
Construction TBD $ 365,000 Complete Streets 2022 2023

Additional Information

Figure 1 - Photo of Rocky Point Dr with cars in queue and stormwater ponding

Figure 1 - Photo of Rocky Point Dr with cars in queue and stormwater ponding