Tampa Theatre from the Cheap Seats Merge Detail Vignette

Revised schedule for Pipe Replacement Project on W North B Street

Posted Date

On Tuesday, February 15 at 9 a.m., a contractor for the Wastewater Department will begin Phase 1 of a project to replace sections of deteriorated wastewater gravity mainline pipes located on W North B Street. The first section to be replaced is W North B Street between N Freemont and N Rome Avenues. This work was originally slated to begin on January 10.

Upon completion of Phase 1, the contractor will begin Phase 2 and relocate to W North B Street between N Albany and N Freemont Avenues. There will be intermittent lane closures on W North B Street during both phases of this project.

Throughout this project the contractor will:

  • Temporarily restore W North B Street daily to maintain access.
  • Have flaggers and signage on-site to reroute traffic around the work areas.
  • Maintain safe access for residences and businesses in the area.

This project, including restoration of the work area, is scheduled for completion by April 5, weather permitting.  The City of Tampa recommends that motorists use alternative routes to avoid traffic congestion. 

Permit #: CWS-22-0000120


For additional information, please contact:
Albert Calloway, Construction Engineer

City of Tampa Contract Administration / Construction Management
(813) 635-3400; albert.calloway@tampagov.net