Temporary Lane Closure of W Gandy Boulevard to begin February 11th 2021 for Driveway Construction

Posted Date

A portion of W Gandy Boulevard between Bayshore Boulevard and S MacDill Avenue will close daily from 9 am to 4 pm beginning on Thursday, February 11, 2021 for driveway construction. A private contractor will be installing a construction entrance on the north side of W Gandy Boulevard between Bayshore Boulevard and S Zion St as the first phase of a 2-phase project.

One (1) westbound lane of W Gandy Boulevard between Bayshore Boulevard and S Zion St will close at 9 am beginning on February 11, 2021.

One (1) westbound lane on W Gandy Boulevard between Bayshore Boulevard and S Zion will be maintained at all times during construction, with delays.

Sidewalks within the work areas will be closed. Pedestrian access will be maintained via signage to other available sidewalks at all times during construction.

It is anticipated that all lanes on W Gandy Boulevard between Bayshore Boulevard and S MacDill Avenue will be open to traffic by 4 pm on Thursday, February 18, 2021, weather permitting. 

Phase 2 will take place at a later date and includes water connection and final driveway construction.

The City of Tampa recommends that motorists use alternate routes to avoid traffic congestion.

Westbound motorists can use W Euclid Avenue or Interbay Boulevard between Bayshore Boulevard and S MacDill Avenue in lieu of W Gandy Boulevard.

ROW-20-0001910