Temporary Lane Closures of S. Himes Ave. and W. Euclid Ave to begin November 3, 2021 for Roadway Construction

Posted Date

The intersection of S. Himes Ave and W. Euclid Ave. will have temporary lane closures from 9 am to 4 pm beginning on Tuesday 11/3/21, for roadway resurfacing.  The City of Tampa’s Mobility Operations Division will be resurfacing the intersection on S. Himes Ave. and W. Euclid Ave.  One (1) direction of traffic will be maintained at all times for Northbound, Southbound,  Eastbound and Westbound traffic. Closures will begin at 9 am on November 3, 2021.

One direction of traffic will be maintained at all times during construction, with delays. 

The sidewalks in the work areas will be open during construction. 

All lanes at S. Himes Ave. and W. Euclid Ave. will reopen to traffic by 4 pm daily. The project should be completed by Wednesday 11/10/21 weather permitting.

The City recommends using alternative routes to avoid traffic congestion.


For additional information, please contact:
City of Tampa’s Mobility Operations Department

(813) 622-1940