In-Progress Projects ¶

Renovated Meeting Rooms
Scheduled completion by November 2023
Existing meeting space will undergo updates including new carpet, paint, new air wall fabric and upgraded lighting. Demolition will be planned for non-event hours and construction walls will surround work areas to provide a sound barrier for noise elimination
NEW Waterfront Meeting Rooms
Scheduled completion by June 2023
Spanning 16,000 square feet, this two-level addition will provide 18 new meeting rooms overlooking the Hillsborough River. Room pairs will include air walls for increased flexibility. The new waterfront rooms will be accompanied by a terrace offering expansive views and outdoor space. Demolition will be planned for non-event hours and construction walls will surround work areas to provide a sound barrier for noise elimination. The addition of a set of new restrooms and a second service elevator will advance facility operations and event needs.
Updates ¶
Progress Videos ¶
Completed Projects ¶
Click on a project link for more detailed information on each project:
Renovated Ballrooms, Renovated Restrooms, Starbucks Coffee Bar, Big Ray’s Fish Camp Restaurant & The Sail Plaza, and Modernization of Exhibit Hall Concession Stands.