This project provides for intersection improvements and a new traffic signal.

The project will provide for the design and construction of two new mast arm traffic signals at the intersection of W Platt St and S Fremont Ave. As part of the project, minor geometric changes will be made as appropriate, including curb bulb-outs, new crosswalks, pedestrian signals, ADA-compliant ramps, detectable warning mats, and drainage modifications. The need for this project was identified by a safety study. The new signals should reduce severe right-angle traffic crashes and provide better transportation network connectivity for all modes.

Costs and Schedule

Phase Firm Cost Funding Source Schedule Start Schedule Finish
Design Element Engineering $147,000 City Mar-21 Mar-22
Construction TBD $500,000 FDOT/City Oct-22 May-23