Manhattan Ave Improvements (Richardson Ave to Interbay Blvd)

Project Location

Manhattan Ave (Richardson Ave to Interbay Blvd)

Project falls within City Council District 4

Project Description

City Project No: 1000980

This project provides for the design and construction of roadway and traffic improvements at the intersection of Interbay Blvd and S Manhattan Ave. The project extends along S Manhattan Avenue approximately 1500 feet south of the intersection connecting to the developer project which extends to Richardson Ave.

The 0.5-mile segment of S Manhattan Ave from north of Richardson Ave to Interbay Blvd is a 2-lane local, residential roadway with a posted speed of 20 mph and is adjacent to MacDill Air Force Base. S Manhattan Ave is a north-south roadway running parallel to West Shore Blvd and provides an alternate north-south traffic circulation route for the Port Tampa area. This project includes many benefits to the community such as:

• roadway resurfacing to improve the resiliency of the neighborhood access to Interbay Blvd
• construction of a new sidewalk along the east side of S Manhattan Ave
• installation of a mid-block crosswalk located near Richardson Ave
• construction of a new southbound left-turn lane and an eastbound left-turn at the intersection of Interbay Blvd and S Manhattan Ave

The project was awarded a 2020 Defense Infrastructure Grant (DIG) in the amount of $340,000.

Public Meeting

The City of Tampa Mobility Department held a Virtual Public Meeting on May 10, 2022, for programmed improvements along Manhattan Ave and Interbay Blvd.  A repeat of the meeting was held on May 11th, 2022.  The virtual meeting presentation can be accessed below.

Contact Information

Project Manager: Robert Hatton, P.E.

If you have questions about this meeting or project, please use the email link below:

Costs and Schedule

Table 1 - Summary of Project Costs and Schedule
Phase Firm Cost Funding Source Schedule Start Schedule Finish
Preliminary Engineering Wade Trim $29,740 City Fall 2016 Summer 2017
Final Design Bala Engineering $150,000 City Spring 2020 Fall 2022
Construction TBD $986,932 City / DIG Winter 2022 Fall 2023