The Lamb Canal has experienced significant erosion over the years and is in need of rehabilitation. Embankment deterioration has reduced the canal’s capacity and increased the risk of further erosion.This project will remove accumulated sediment and stabilize the canal banks in targeted areas to prevent future erosion and help restore capacity. A future phase may include replacing and upsizing the drainage pipes at W. Bay to Bay Boulevard and S. Manhattan Avenue to help alleviate frequent nuisance flooding at the intersection.
The project is currently at a 60% design status. Upon completion, the project will relieve flooding along local and collector roadways thereby improving traffic safety, and water quality draining to Lake Dundee and Tampa Bay, as well as provide for a low-maintenance and resilient drainage system.
Community Benefits
Flooding Relief
Contact Info
Contact Name
Alex Awad
Contact Phone
813-380-6114
Contact Email
Project ID
1001171
Department ID
SW50006
Project Type
Status
Project Phase
Construction Fiscal Year
On Hold
Multi Year Project
Yes
Council District
4
Neighborhood
Schedule and Costs
Project Phase
Planning
Design
Procurement
Construction
Closeout
Current Phase:
Planning
Funding Source
Stormwater Improvement Fee
Funded Project
Yes
Budget Year
2022