Looking up at palm trees at Curtis Hixon Park

30th St Sligh Intersection Improvements

Primary Details

Description

This project provides for design and construction of capacity and multimodal improvements along the E Hanna Ave corridor from N 22nd St to N 30th Sr., along the 24th St from Hanna Ave to Sligh Ave, and at the intersection of Sligh Ave and 30th St. The project includes the following proposed improvements:

  1. Hanna Avenue – 22nd Street to 30th Street:
    • Roadway milling and resurfacing.
    • Westbound Left Turn Lane into the new City Center at 2515 Hanna Ave.
    • Intersection improvements at the intersection of Hanna Ave at N 22nd St and Hanna Ave at N 30th St
  2. 24th Street – Hanna Avenue to Sligh Avenue:
    • Sidewalk along the west side of 24th St
    • All Way Stop Signs at “T” intersection along 24th St
  3. Intersection at the Sligh Avenue and 30th Street:
    • New Traffic Signal
    • Northbound Left-Turn Lane.
Community Benefits
Complete Streets & Safety Improvements

Contact Info

Contact Name
Riley Parks, P. E.
Contact Phone
813-274-8265
Project ID
1002148
Department ID
TRANS20148
Project Type
Project Phase
Construction Fiscal Year
2027
Multi Year Project
No
Council District
5
Neighborhood

Schedule and Costs

Project Phase
Planning
Design
Procurement
Construction
Closeout
Current Phase: Design
Planned Start Date
Planned End Date
Funding Source
Local Option Gas Tax
Estimated Cost
$281,344
Funded Project
No
Funding Comments
No additional funding comments