Primary Details
Description
Approximately 4,921 Linear Feet of water mains ranging from 2 to 6 inches in diameter will be replaced and upgraded. The project area and the streets impacted by this project are shown on the attached map.
Community Benefits
The Empedrado St Project will improve the City of Tampa’s water distribution system by replacing the existing water mains and increasing the capacity of the system. This project will replace the aging water mains in this area with new and larger diameter water mains, improving water pressure and water quality while reducing the number of service interruptions that might have been caused by main breaks or leakage. It will also improve our ability to serve a growing population.
Contact Info
Contact Name
Liz Hall
Contact Phone
813-557-3979
Contact Email
Project ID
WTR-24-0018
Department ID
WTR-24-0018
Project Type
Project Phase
Construction Fiscal Year
2026
Multi Year Project
No
Council District
4
Neighborhood
Schedule and Costs
Project Phase
Planning
Design
Procurement
Construction
Closeout
Current Phase:
Construction
Planned Start Date
Planned End Date
Funding Source
PIPES
Estimated Cost
$790,574
Funded Project
No