This project provides for the replacement of the gravity sewer upstream of the Executive Park pumping station.
Community Benefits
The gravity main replacement project will replace aging, deteriorated pipelines that have reached the end of their useful life and are susceptible to failure that can cause wastewater overflows that may impact public health, safety, and environment. The new gravity main will reduce leaks that allow groundwater to enter the collections system and lower the energy costs needed to treat and pump the additional groundwater.
Contact Info
Contact Name
Charlie Lynch
Contact Phone
8132748916
Contact Email
Project ID
1002388
Department ID
WW1002388
Project Type
Status
Project Phase
Construction Fiscal Year
2022
Multi Year Project
No
Council District
6
Neighborhood
Schedule and Costs
Project Phase
Planning
Design
Procurement
Construction
Closeout
Current Phase:
Closeout
Planned Start Date
Planned End Date
Funding Source
PIPES
Estimated Cost
$2,500,000
Funded Project
Yes
Budget Year
2022
Contract Number
22-C-00005