Project Location ¶

Project falls within City Council District 5
Project Description
City Project No: 1001179-005 LAP: FPN 443582-1
This project provides for safety improvements, traffic calming, and pedestrian facilities to establish a safe walking route to school.
Under Sulphur Springs Safe Routes to School program, the City of Tampa is proposing to enhance the safety and quality of the pedestrian routes along N 12th St from E Fairbanks St to E Yukon St. Improvements will include new 5 ft wide concrete sidewalks along the east side of 12th St from E Seward St to N 13th St. Intersection improvements will be installed at N 12th St and Fairbanks St, N 12th St and E Seward St, N 12th St and E Yukon St, N 11th St and E Yukon St, and N 13th St and E Seward St.
Contact Information ¶
Project Manager: Jola Olbinska, P. E.
If you have questions about this meeting or project, please use the email link below:
Costs and Schedule ¶
Phase | Firm | Cost | Funding Source | Schedule Start | Schedule Finish |
---|---|---|---|---|---|
Design | FTE | $218,210 | Central / East | Jul-20 | Apr-22 |
Construction | TBD | $554,382 | LAP | Feb-23 | Dec-23 |