TECO Streetcar at Dick Greco Plaza

North Ashley Pond Expansion

Primary Details

Description
Currently there is substantial flooding on N Tampa St east of the existing Ashley stormwater pond. The project consists of the expansion of the existing stormwater pond to alleviate flooding in the neighborhood.
Community Benefits
Flooding Relief | Improve Traffic Flow and Safety | Water Quality | Restore Natural Habitats | Enhance Resiliency

Contact Info

Contact Name
Jeff DeBosier
Contact Phone
813-274-8428
Project ID
1001955
Department ID
SW60004
Project Type
Project Phase
Construction Fiscal Year
2027
Multi Year Project
No
Council District
7
Neighborhood

Schedule and Costs

Project Phase
Planning
Design
Procurement
Construction
Closeout
Current Phase: Construction
Planned Start Date
Planned End Date
Funding Source
Stormwater Improvement Fee
Estimated Cost
$90,000
Funded Project
No
Funding Comments
No additional funding comments
Location

28.038563675084, -82.460768369744

Project Location