Tampa Theatre from the Cheap Seats Merge Detail Vignette

S.E. Seminole Heights Flooding Relief (GMP 1)

Primary Details

Description
The project includes approximately 16,300 linear feet of new stormwater culverts with associated laterals, inlets, system interconnections, and utility conflict‑resolution relocations. It also incorporates transportation‑related elements, sustainability treatment components, and upgrades to existing water infrastructure. In addition, the project will replace roughly 11,700 linear feet of water mains located outside the stormwater construction corridors. The City secured cooperative funding support from the Southwest Florida Water Management District (SWFWMD) to implement these improvements.
Community Benefits
Flooding Relief | Pollution Reduction | Infrastructure Upgrades | Enhance Traffic/Pedestrian Safety

Contact Info

Contact Name
Albert Calloway | Saad El Bakkouri
Contact Phone
813-630-3902
Project ID
1001151
Department ID
SW40003
Project Type
Project Phase
Construction Fiscal Year
2022
Multi Year Project
Yes
Council District
6
Neighborhood

Schedule and Costs

Project Phase
Planning
Design
Procurement
Construction
Closeout
Current Phase: Construction
Planned Start Date
Planned End Date
Funding Source
Stormwater Improvement Fee
Estimated Cost
$33,535,000
Funded Project
Yes
Contract Number
19-C-00012
Location

27.996220292928, -82.453849726501

Project Location