Peter O Knight Project

Primary Details

Description

Approximately 4,683 Linear Feet of water mains ranging from 12 to 16 inches in diameter will be replaced and upgraded. The project area and the streets impacted by this project are shown on the attached map.

Community Benefits

The Peter O Knight Project will improve the City of Tampa’s water distribution system by replacing the existing water mains and re-routing the mains, so they do not impact the runway. This project will replace the water mains in this area with new water mains, improving water pressure and water quality while reducing the number of service interruptions that might have been caused by main breaks or leakage. It will also improve our ability to serve a growing population.

Contact Info

Contact Name
Nadine Maghsoudlou
Contact Phone
813-274-8970
Project ID
W70052
Department ID
W70052
Project Type
Status
Project Phase
Construction Fiscal Year
2025
Multi Year Project
No
Council District
4
Neighborhood

Schedule and Costs

Project Phase
Planning
Design
Procurement
Construction
Closeout
Current Phase: Planning
Funding Source
PIPES
Estimated Cost
$960,089
Funded Project
No
Location

27.910202749906, -82.455743920498

Project Location