Approximately 10,113 linear feet of water mains ranging from 2 to 8 inches in diameter will be replaced and upgraded.
Community Benefits
The SE Lake Carroll WM Replacement project will improve the City of Tampa’s water distribution system by replacing the existing water mains. This project will replace the aging water mains in this area with new and larger diameter water mains, improving water pressure, water quality, and increasing the capacity of the system while reducing the number of service interruptions that might have been caused by main breaks or leakage.
Contact Info
Contact Name
Andre Bien-Aime
Contact Phone
813-274-8593
Contact Email
Project ID
WTR-25-0002
Department ID
WTR-25-0002
Project Type
Status
Project Phase
Construction Fiscal Year
2027
Multi Year Project
No
Schedule and Costs
Project Phase
Planning
Design
Procurement
Construction
Closeout
Current Phase:
Design
Planned Start Date
Planned End Date
Funding Source
PIPES
Estimated Cost
$3,540,279
Funded Project