Party Deck Sunset Wide

All Capital Improvement Projects

This is list of our Capital Improvement Projects to learn more visit our Capital Improvement Projects landing page.

Displaying 76 - 100 of 208
Title Project Type Project Phase Planned Start Date Planned End Date Status Council District Estimated Cost Fiscal Year Funding Source Description
Armory Gardens Water P3: Procurement Project Startup 6 $1156019.80 2027 PIPES Approximately 4,136 linear feet of water mains ranging from 2 to 6 inches in diameter will be replaced and upgraded.
S.E. Seminole Heights Flooding Relief (GMP 1) Stormwater Engineering P4: Construction Construction in Progress 6 $30000000.00 2022 Stormwater Improvement Fee Design and construction of approximately 16,300 LF of stormwater culverts with associated laterals, inlets, interconnections to existing stormwater system, associated utility conflict resolution relocations, transportation elements, water main replacement upgrades and sustainability treatment elements. The project will also include certain transportation elements as well as the replacement of approximately 11,700 LF of water mains not in the same corridors as the proposed stormwater infrastructure
30th St (E Busch Blvd to E Bougainvillea Ave) Segment 1 (Resurfacing) Transportation P5: Closeout Closeout 7 $3334945.60 2024 Local Option Gas Tax This project provides for complete street roadway improvements to enhance safety and multimodal connectivity, including sidewalks and trails, bicycle facilities, enhanced crosswalks, and other safety measures. Landscaping and green infrastructure components are also included.
DLTWTF Master Plan Task Order 013 Filter Improvements Water P4: Construction Construction in Progress 5 $119121495.00 2024 PIPES The DLTWTF Master Plan Filter Improvements project will optimize facility performance capabilities, improve water quality and expand our water treatment capacity. This project will rehabilitate and replace existing infrastructure and eliminate deteriorating facilities and equipment to increase operational and maintenance efficiency. New infrastructure upgrades will increase our capacity to produce drinking water and we will also add new back-up systems to strengthen our resiliency when faced with a natural disaster or other emergency. New treatment processes will also be explored to achieve the twin goals of enhancing the taste and odor of our drinking water while reducing the use of water treatment chemicals.
Howard F. Curren AWTP Master Plan Improvements, Phase 1, Design-build GMP No. 2 Wastewater P4: Construction Construction in Progress 5 $77604828.00 2023 PIPES This project provides for the rehabilitation of the main pumping station and the high purity oxygen (HPO) reactors at the Howard F. Curren AWTP. The project will include replacement of the seven (7) main sewage pumps, blowers, spent cooling water pumps, process piping and valves, mixers, aerators and diffusers, concrete repairs and coatings, the construction of a new electrical building and transformer structure, and the installation of new electrical and control systems.
Willow Ave WM Replacement Water P2: Design 30% Design Completion 5 $7888229.34 2028 PIPES Approximately 17,373 linear feet of water mains ranging from 2 to 12 inches in diameter will be replaced and upgraded.
Interbay Blvd (Manhattan Ave to Tanker Way) Transportation P5: Closeout Cancelled 4 $135000.00 2024 Transportation Impact Fees

This project provides for operational improvements by widening for a right turn lane.

Salcines Park Improvements Parks & Recreation P4: Construction Construction in Progress 5 $1267798.68 2025 Community Redevelopment Agency Improvements to Salcines Park based on public input.
Lower Peninsula Water P5: Closeout Closeout 4 $1655134.57 2023 PIPES The Lower Peninsula project will improve the City of Tampa’s water distribution system by replacing the existing water mains and increasing the capacity of the system. It will also improve our ability to serve a growing population. Approximately 3,638 Linear Feet of water mains ranging from 2 to 16 inches in diameter will be replaced and upgraded.
High Service Pump Station (GMP 2) Water P5: Closeout Closeout 5 $65985127.00 2021 PIPES The High Service Pump Station project will optimize facility performance capabilities, improve water quality and expand our water treatment capacity. This project will rehabilitate and replace existing infrastructure and eliminate deteriorating facilities and equipment to increase operational and maintenance efficiency. New infrastructure upgrades will increase our capacity to produce drinking water and we will also add new back-up systems to strengthen our resiliency when faced with a natural disaster or other emergency. New treatment processes will also be explored to achieve the twin goals of enhancing the taste and odor of our drinking water while reducing the use of water treatment chemicals.
W Cypress Street Resurfacing (Zone 1) From N Obrien St to N Himes Ave Transportation P2: Design 30% Design Completion 6 $6035773.00 TBD Tax - Other This is a subproject of the Hillsborough County Resurfacing Tax Project funded by the AFT Surtax Network Operating Fund. The project provides pavement resurfacing, pedestrian accessibility and safety improvements along the W Cypress street corridor, spanning approximately 1.9 miles from N Obrien st to N Himes Ave. This section of W Cypress is a collector roadway serving as a critical access route for the Tampa International Airport, Carver City Lincoln Gardens, North Bon Air, Midtown and Oakford Park neighborhoods. The project will include:
• Roadway resurfacing
• Improved pavement markings
• ADA pedestrian ramps
DLT Master Plan DB Task Order 010 Ozone Improvements Water P2: Design 90% Design Completion 5 $57700738.00 2026 PIPES The DLTWTF Master Plan Ozone Improvements project will optimize facility performance capabilities, improve water quality and expand our water treatment capacity. This project will rehabilitate and replace existing infrastructure and eliminate deteriorating facilities and equipment to increase operational and maintenance efficiency. New infrastructure upgrades will increase our capacity to produce drinking water and we will also add new back-up systems to strengthen our resiliency when faced with a natural disaster or other emergency. New treatment processes will also be explored to achieve the twin goals of enhancing the taste and odor of our drinking water while reducing the use of water treatment chemicals.
Beach Park Drainage Improvements Stormwater Engineering P5: Closeout Closeout 6 $1000000.00 2022 Stormwater Improvement Fee

This project provides for the construction of new pipes and inlets connecting to the existing system on Swann Avenue to alleviate flooding in the area.

Downtown Core Complete Streets (Brorein St from Ashley Dr to Morgan St) Transportation P5: Closeout Closeout 5 $1900000.00 2025 Local Option Gas Tax This project provides for multimodal and safety improvements. General maintenance and Complete Streets improvements to several streets and incorporated in this project in the Downtown Core: Brorein St from Ashley Dr to Morgan St. As part of the project, these roadways will be resurfaced to remove deficiencies and provide a newly finished driving surface. This project will also include multimodal improvements to make these corridors safer for all users in accordance with the City’s Vision Zero initiative. • Parking Protected Buffered Bike Lanes with conflict markings to allow for safer cycling; • Pedestrian Bulb-outs to shorten pedestrian crossing distances; • Enhanced Crosswalks to provide pedestrians with more visibility; • Traffic Calming features to control speeds and reduce the likelihood of fatal crashes; • Reconstructed Curb Ramps to provide ease of use and accessibility to people with disabilities.
DLTWTF MP Task Order 008 Raw Water Pump Station Water P2: Design 90% Design Completion 5 $73814773.00 2027 PIPES The DLTWTF Master Plan Improvements project will optimize facility performance capabilities, improve water quality and expand our water treatment capacity. This project will rehabilitate and replace existing infrastructure and eliminate deteriorating facilities and equipment to increase operational and maintenance efficiency. New infrastructure upgrades will increase our capacity to produce drinking water and we will also add new back-up systems to strengthen our resiliency when faced with a natural disaster or other emergency. New treatment processes will also be explored to achieve the twin goals of enhancing the taste and odor of our drinking water while reducing the use of water treatment chemicals.
Clark and Fairoaks Stormwater Engineering P2: Design 90% Design Completion 4 $350000.00 2027 Stormwater Improvement Fee Replacing the failed pipes and construction of new pipes and inlets to alleviate the flooding situation
Sitewide Electrical Improvement Water P4: Construction Final Contract Review & Approval 5 $52935137.00 2026 PIPES The TECO House and Sitewide Electric project will optimize facility performance capabilities, improve water quality and expand our water treatment capacity. This project will rehabilitate and replace existing infrastructure and eliminate deteriorating facilities and equipment to increase operational and maintenance efficiency. New infrastructure upgrades will increase our capacity to produce drinking water and we will also add new back-up systems to strengthen our resiliency when faced with a natural disaster or other emergency. New treatment processes will also be explored to achieve the twin goals of enhancing the taste and odor of our drinking water while reducing the use of water treatment chemicals.
Green Spine Cycle Track, Segment 3C Transportation P5: Closeout Closeout 5 $2544487.00 2024 Multiple Funding This project provides for a bi-directional cycle track along 15th St. from 13th Avenue to 21st Ave.
Church Pumping Station Rehabilitation (Year 3) Wastewater P2: Design 30% Design Completion 4 $1200000.00 2027 PIPES The project provides for the rehabilitation of the wastewater pumping station at 3901 Elmwood Terr. Project will include replacement of pumps, piping, valves, and electrical improvements to ensure continued reliability of the station.
Convention Center Renovations Convention Center & Tourism P5: Closeout Closeout 5 $38134770.53 2021 Tourist Development Taxes

This project provides for multi-year renovations at the Tampa Convention Center including but not limited to restroom, elevator, & meeting room upgrades, air handler & door replacement, painting, and other improvements as needed.

Hanna Avenue Phase 1 (24th St to CSX RR) Transportation P2: Design 30% Design Completion 5 $1670096.00 2030 Yet to be Determined Reprofiling of Hanna Avenue in front of City Center
TCC Renovations Phase II Convention Center & Tourism P5: Closeout Closeout 5 $3983058.00 2021 Tourist Development Taxes

This project provides for multi-year renovations at the Tampa Convention Center including but not limited to restroom, elevator, & meeting room upgrades, air handlers & chillers, painting, and other.

122nd Ave Pumping Station Rehabilitation Wastewater P5: Closeout Closeout $1260000.00 2025 PIPES This project provides for the rehabilitation of 122nd Avenue wastewater pumping station located at 2715 E 122nd Ave. Project will include replacement of pumps, piping, valves, and electrical improvements to ensure the continued reliability of the station.
30th St and Fowler - USF FM Extension Wastewater P4: Construction Construction in Progress 7 $2500000.00 2025 PIPES Replace and extend the existing 12” USF force main on 30th St. south of Fowler Ave. to north of 109th Ave with 2,150 LF of 18” PVC force main.
Floribraska Water P5: Closeout Closeout 5 $1794339.00 2023 PIPES

The Floribraska project will improve the City of Tampa’s water distribution system by replacing the existing water mains and increasing the capacity of the system. It will also improve our ability to serve a growing population. Approximately 2,682 Linear Feet of water mains 8 inches in diameter will be replaced and upgraded.