Project Location ¶

Project falls within City Council District 6
Project Description
City Project No: 1001162
This project will upgrade roadway safety and provide for bike/pedestrian connectivity. It includes the enclosure of the ditches on the east and west sides of N Glen Ave between W Green St and W Beach St and the new sidewalk along the west side of N Glen Ave.
Public Meeting ¶
The City of Tampa Mobility Department held a Virtual Public Meeting on June 1, 2022, for Sidewalk & Safety Improvements along Glen Ave from W Green St to W Beach St. The virtual meeting presentation can be accessed below.
Contact Information ¶
Project Manager: Jola Olbinska, P. E.
If you have questions about this meeting or project, please use the email link below:
Costs and Schedule ¶
Phase | Firm | Cost | Funding Source | Schedule Start | Schedule Finish |
---|---|---|---|---|---|
Design | PGA | $145,879.59 | Central/East | Apr-19 | Jul-22 |
Construction | TBD | $414,751 | TBD | TBD | TBD |