Tampa Convention Center

P3: Procurement

Contract Negotiations

Flooding Relief | Improve Traffic Flow and Safety
Council: 5Est. Cost: $1,500,000Fund Source: Stormwater Improvement Fee

Project Startup

The Armory Gardens project will improve the City of Tampa's water distribution system by…
Council: 6Est. Cost: $1,156,020Fund Source: PIPES
Flooding Relief | Improve Traffic Flow and Safety
Council: 4Est. Cost: $1,500,000Fund Source: Stormwater Improvement Fee
This project will replace the aging water mains in this area with new and larger diameter…
Council: 5Est. Cost: $2,557,137Fund Source: PIPES
This project will provide updated pedestrian curb ramps to comply with ADA standards and…
Council: 7Est. Cost: $834,200Fund Source: Tax - Other
The Heights WM Improvent Projet (Phase II) will improve the City of Tampa’s water…
Council: 5Est. Cost: $4,534,148Fund Source: PIPES

Consultant/Contractor Selection Process

Improve Flood Control | Enhanced Resiliency | Enhanced Reliability
Council: 7Est. Cost: $1,600,000Fund Source: Multiple Funding
The treatment plant project will restore the plant’s reliability by replacing aging…
Council: 5Est. Cost: $31,750,000Fund Source: PIPES
The Peter O Knight Project will improve the City of Tampa’s water distribution system by…
Council: 4Est. Cost: $960,089Fund Source: PIPES

Permitting/Submittals Approval

The pumping station rehabilitation project will restore the station’s reliability by…
Council: 6Est. Cost: $776,000Fund Source: PIPES
Flooding Relief | Improve Traffic Flow and Safety
Council: 6Est. Cost: $1,500,000Fund Source: Stormwater Improvement Fee