Lois Ave. Sidewalk

The project consists of construction of 700 ft. of a new 6 ft. sidewalk to fill the gap on the east side of N. Lois Ave from W. Spruce St. to International Dr. Due to the existing cross-slopes from the back of curb to adjacent parking lot, a retaining wall will be necessary at the back of sidewalk. Coordination with the adjacent property owner to obtain 3 temporary construction easements will be needed due to impacts to landscaping, irrigation, and to the existing driveway location.

The sidewalk segment was also identified in the City of Tampa Walk-Bike Plan Phase I Final Report. Engineering services were required for design of retaining wall segments necessary to accommodate a sidewalk.