Tampa Convention Center Skyline

All Capital Improvement Projects

This is list of our Capital Improvement Projects to learn more visit our Capital Improvement Projects landing page.

Displaying 76 - 100 of 215
Title Project Type Project Phase Planned Start Date Planned End Date Status Council District Estimated Cost Fiscal Year Funding Source
7th Avenue from 17th to 26th Street Transportation P1: Planning Planning 5 $788218.00 2026 Community Redevelopment Agency
Swann Pumping Station Generator Installation Wastewater P3: Procurement Permitting/Submittals Approval 6 $776000.00 2026 PIPES
Krause Pumping Station Standby Generator Wastewater P5: Closeout Closeout 5 $1322592.00 2022 PIPES
Sherwood Heights PS FM Relocation Wastewater P2: Design 90% Design Completion 7 $250000.00 2026 PIPES
Howard F. Curren AWTP Master Plan Improvements, Phase 2, Design-build GMP No. 1 Wastewater P3: Procurement Consultant/Contractor Selection Process 5 $31750000.00 2027 PIPES
Howard F. Curren AWTP Master Plan Improvements, Phase 1, Design-build GMP No. 4 Wastewater P4: Construction Construction in Progress 5 $115000000.00 2025 PIPES
Franklin St and Fort Brooke Garage - Blank Out Signs Transportation P2: Design 90% Design Completion 5 2026 Yet to be Determined
O'Brien St - Segment 1 (Cypress St. to Spruce St.) Transportation P5: Closeout Closeout 6 $651450.00 2025 Other Agencies
N 24th Street (Hanna Ave to Sligh Ave) Transportation P2: Design 60% Design Completion 5 $400000.00 2027 Multiple Funding
Kirby St. FM Replacement Project Wastewater P5: Closeout Closeout $1565354.00 2024 PIPES
Downtown Core Complete Streets (Brorein St from Ashley Dr to Morgan St) Transportation P5: Closeout Closeout 5 $1900000.00 2025 Local Option Gas Tax
Idlewild Pumping Station Force Main Extension Wastewater P5: Closeout Closeout 6 $640000.00 2024 PIPES
SE Lake Caroll Water P1: Planning Planning $3435556.12 2026 PIPES
MLK Resurfacing from Air Cargo to Dale Mabry Transportation P3: Procurement Contract Negotiations 6 $950000.00 2026 Local Option Gas Tax
Downtown Core Complete Streets (Florida Ave from Channelside Dr to Jackson St) Transportation P2: Design 60% Design Completion 5 $1000000.00 2026 Yet to be Determined
Foundation for Tampa’s Neighborhoods Project_Virginia Park Area Water P5: Closeout Closeout 4 $8677855.56 2022 PIPES
Rocky Point Dr Complete Streets (South of Courtney Campbell Causeway) Transportation P5: Closeout Closeout 6 $798400.00 2023 Transportation Impact Fees
Beach Place Water P2: Design 30% Design Completion 4 $387232.31 2026 PIPES
Sidewalks- Hubert St (W Cypress to W Main St) Transportation P5: Closeout Closeout 6 $320000.00 2025 Transportation Impact Fees
Sidewalks- Prescott St (S Kissimmee St to West Shore Blvd) Transportation P5: Closeout Closeout 4 $32000.00 2023 Sidewalk In-Lieu Fees
Wastewater Pumping Station Rehabilitation Prescott PS Wastewater P3: Procurement Permitting/Submittals Approval 4 $3089233.00 2026 PIPES
West Riverside Heights Gravity Sewer Rehab by CIPP Lining Wastewater P5: Closeout Closeout 6 $810000.00 2024 PIPES
DLTWTF Building Improvements Water P5: Closeout Closeout 5 $3160168.00 2021 PIPES
Wastewater Pumping Station Rehabilitation Parke East PS Wastewater P4: Construction Construction in Progress $1801300.00 2025 PIPES
Willow Ave Water P1: Planning Planning 5 $7557672.79 2026 PIPES