Tampa Convention Center Gasparilla

All Capital Improvement Projects

This is list of our Capital Improvement Projects to learn more visit our Capital Improvement Projects landing page.

Displaying 76 - 100 of 219
Title Project Type Project Phase Planned Start Date Planned End Date Status Council District Estimated Cost Fiscal Year Funding Source
Green Spine Cycle Track, Segment 3B Transportation P5: Closeout Closeout 5 $1645831.00 2024 Multiple Funding
Ola Ave Water P2: Design 60% Design Completion 5 $15675175.00 2026 PIPES
Salcines Park Improvements Parks & Recreation P4: Construction Construction in Progress 5 $1267798.68 2025 Community Redevelopment Agency
FY20 CIP Water Main Improvements Design-Build_W Riverside Heights – GMP 5 Water P4: Construction Construction in Progress 6 $4912885.00 2026 PIPES
109th St Pumping Station Force Main Extension Wastewater P5: Closeout Closeout 7 $480000.00 2024 PIPES
7th Ave Water P2: Design 30% Design Completion 5 $13112980.00 2026 PIPES
Brorein St Bridge (#105501) Phase 2 Mechanical/ Electrical Rehabilitation Transportation P2: Design 90% Design Completion 4 $9930000.00 TBD Local Option Gas Tax
Sherwood Heights PS FM Relocation Wastewater P2: Design 90% Design Completion 7 $250000.00 2026 PIPES
Clark and Fairoaks Stormwater Engineering P2: Design 90% Design Completion 4 $350000.00 2025 Stormwater Improvement Fee
14th St (Av Republica De Cuba) & 21st Ave Transportation P5: Closeout Closeout 5 $353000.00 2025 Local Option Gas Tax
Downtown Core Complete Streets (Tampa St from Brorein St to Jackson St) Transportation P2: Design 60% Design Completion 5 $1000000.00 2026 Yet to be Determined
Cory Lakes III Pumping Station Rehabilitation Wastewater P1: Planning Planning 7 $225000.00 2027 PIPES
Greenways, Trail & Gateway Sign - New Tampa Nature Park Parks & Recreation P2: Design 90% Design Completion 7 $500000.00 2025 Community Investment Taxes
43rd St Ditch Rehabilitation Stormwater Engineering P4: Construction Construction in Progress 5 $2280000.00 2025 Stormwater Improvement Fee
NTCB 99th Ave -West Pond Expansion Stormwater Engineering P2: Design 30% Design Completion 7 $50000.00 2025 Stormwater Improvement Fee
Interbay Blvd (Manhattan Ave to Tanker Way) Transportation P5: Closeout Cancelled 4 $135000.00 2024 Transportation Impact Fees
NTCB 99th Ave East -Pond Expansion Stormwater Engineering P5: Closeout Closeout 7 $100000.00 2024 Stormwater Improvement Fee
SE Lake Caroll Water P2: Design 30% Design Completion $3435556.12 2027 PIPES
Willow Ave Water P1: Planning Planning 5 $7557672.79 2026 PIPES
NTCB Elmer Pond Expansion Stormwater Engineering P2: Design 30% Design Completion 7 $90000.00 2025 Stormwater Improvement Fee
Clark Street and 30th Street Pipe Relocation Stormwater Engineering P5: Closeout Closeout 5 $225000.00 2024 Stormwater Improvement Fee
Sligh Ave & 30th St (Signal) Transportation P5: Closeout Closeout 5 $300000.00 2025 Local Option Gas Tax
Convention Center Renovations Convention Center & Tourism P5: Closeout Closeout 5 $38134770.53 2021 Tourist Development Taxes
Riveredge Pumping Station Rehabilitation (Year 2) Wastewater P4: Construction Construction in Progress 7 $2140000.00 2025 PIPES
30th St and Fowler - USF FM Extension Wastewater P4: Construction Construction in Progress 7 $2500000.00 2025 PIPES