All Capital Improvement Projects
This is list of our Capital Improvement Projects to learn more visit our Capital Improvement Projects landing page.
| Title | Project Type | Project Phase | Planned Start Date | Planned End Date | Status | Council District | Estimated Cost | Fiscal Year | Funding Source | Description |
|---|---|---|---|---|---|---|---|---|---|---|
| Interbay Blvd (Manhattan Ave to Tanker Way) | Transportation | P5: Closeout | Cancelled | 4 | $135000.00 | 2024 | Transportation Impact Fees | This project provides for operational improvements by widening for a right turn lane. |
||
| 14th St (Av Republica De Cuba) & 21st Ave | Transportation | P5: Closeout | Closeout | 5 | $353000.00 | 2025 | Local Option Gas Tax | This project is located at the intersection of N 14th St (ARDC) & E 21st Ave is to upgrade the existing concrete strain pole and span wire system using the galvanized steel pole and mast arm relocated from N Boulevard & W Ross Ave. The project will include new vehicular traffic signal heads along with new pedestrian signal heads and ADA compliant pedestrian ramps. | ||
| MacDill Ave & Gandy Blvd - Traffic Signal Upgrade | Transportation | P2: Design | 60% Design Completion | 4 | $900000.00 | 2027 | Other Agencies | This project includes design and replacement of traffic signals to improve safety and enhance access for the community. The project includes left turn signals, marked crosswalks, pedestrian signals, ADA-compliant ramps, and detectable warning mats. | ||
| Busch Blvd Trunk Sewer Rehabilitation by CIPP Lining | Wastewater | P2: Design | 30% Design Completion | 7 | $1500000.00 | 2027 | PIPES | This project includes the rehabilitation of approximately 4,660 linear feet of 8-inch, 1,130 linear feet of 10-inch, 504 linear feet of 12-inch, 1,421 linear feet of 18-inch, 1,751 linear feet of 21-inch, 855 linear feet of 24-inch and 2,624 linear feet of 30-inch diameter gravity sewers. | ||
| Drew Park CRA - Mobility, Connectivity, and Safety Improvements | Transportation | P2: Design | 60% Design Completion | 6 | $9504000.00 | 2027 | Community Redevelopment Agency | To identify and recommend potential mobility, connectivity, and safety projects, including project estimates, and to identify/recommend/provide quick bid options for improvements for improvements within public rights-of-way throughout the Drew Park Community Redevelopment Area (CRA). | ||
| Empedrado St | Water | P4: Construction | Permitting/Submittals Approval | 4 | $790573.70 | 2026 | PIPES | Approximately 4,921 Linear Feet of water mains ranging from 2 to 6 inches in diameter will be replaced and upgraded. The project area and the streets impacted by this project are shown on the attached map. | ||
| FY20 CIP Water Main Improvements Design-Build_12th St – GMP 5 | Water | P5: Closeout | Closeout | 5 | $5596767.00 | 2026 | PIPES | Approximately 15,960 Linear Feet of water mains ranging from 2 to 8 inches in diameter will be replaced and upgraded. | ||
| Floribraska Ave (Tampa St to 9th St) | Transportation | P5: Closeout | Closeout | 5 | $2399631.00 | 2025 | Multiple Funding | This project provides for multimodal and safety improvements including on-street bicycle lanes. | ||
| Downtown Interchange Wastewater Collection System Rehabilitation by CIPP Lining | Wastewater | P5: Closeout | Closeout | 5 | $600000.00 | 2023 | PIPES | This project includes the rehabilitation of approximately 9,844 linear feet of 8-inch and 10-inch diameter gravity sewers and the rehabilitation of 46 manholes. | ||
| Gray St Bike Blvd. (West Shore Blvd to Rome Ave) | Transportation | P5: Closeout | Closeout | 6 | $500000.00 | 2024 | Westshore DRI | This project provides for a bike boulevard connecting Westshore to West Tampa. | ||
| Hanna Avenue Phase II (22nd St to 30th St) | Transportation | P2: Design | 90% Design Completion | 5 | $3311065.00 | TBD | Yet to be Determined | This project provides for design and construction of capacity and multimodal improvements along the E Hanna Ave corridor from N 22nd St to N 30th Sr., along the 24th St from Hanna Ave to Sligh Ave, and at the intersection of Sligh Ave and 30th St. The project includes the following proposed improvements: 1. Hanna Avenue – 22nd Street to 30th Street: • Roadway milling and resurfacing. • Westbound Left Turn Lane into the new City Center at 2515 Hanna Ave. • Intersection improvements at the intersection of Hanna Ave at N 22nd St and Hanna Ave at N 30th St 2. 24th Street – Hanna Avenue to Sligh Avenue • Sidewalk along the west side of 24th St • All Way Stop Signs at “T” intersection along 24th St 3. Intersection at the Sligh Avenue and 30th Street • New Traffic Signal • Northbound Left-Turn Lane. | ||
| 30th St Sligh Intersection Improvements | Transportation | P2: Design | 90% Design Completion | 5 | $281344.00 | 2027 | Local Option Gas Tax | This project provides for design and construction of capacity and multimodal improvements along the E Hanna Ave corridor from N 22nd St to N 30th Sr., along the 24th St from Hanna Ave to Sligh Ave, and at the intersection of Sligh Ave and 30th St. The project includes the following proposed improvements: 1. Hanna Avenue – 22nd Street to 30th Street: • Roadway milling and resurfacing. • Westbound Left Turn Lane into the new City Center at 2515 Hanna Ave. • Intersection improvements at the intersection of Hanna Ave at N 22nd St and Hanna Ave at N 30th St 2. 24th Street – Hanna Avenue to Sligh Avenue • Sidewalk along the west side of 24th St • All Way Stop Signs at “T” intersection along 24th St 3. Intersection at the Sligh Avenue and 30th Street • New Traffic Signal • Northbound Left-Turn Lane. | ||
| Lantana-Poinsettia Pump Station | Stormwater Engineering | P2: Design | 90% Design Completion | 5 | $200000.00 | 2027 | Stormwater Improvement Fee | This project provides for property acquisition and construction of a new collection system and new pump station to replace the temporary pump and force main connecting the existing drainage system on North 11th Street. | ||
| Peter O Knight Project | Water | P3: Procurement | Consultant/Contractor Selection Process | 4 | $960089.00 | 2027 | PIPES | Approximately 3,218 linear feet of water mains ranging from 12 to 16 inches in diameter will be replaced. | ||
| Manhattan Ave (Richardson Ave to Interbay Blvd) | Transportation | P5: Closeout | Cancelled | 4 | $1000000.00 | 2027 | Transportation Impact Fees | This project provides for the design of roadway construction plans for an existing unimproved right of way to provide an alternative north-south traffic circulation route for the Port Tampa Area. |
||
| Brorein St Bridge (#105501) Phase 2 Mechanical/ Electrical Rehabilitation | Transportation | P2: Design | 90% Design Completion | 4 | $9930000.00 | TBD | Local Option Gas Tax | This project provides for structural rehabilitation as well as rehabilitation of the mechanical and electrical systems. This project will also create safe multimodal access across the river by widening the sidewalks on both sides of the bridge to about 9 feet wide. | ||
| The Heights WM Improvement Project Along Florida Ave from Scott St to Palm Ave (Phase I) | Water | P4: Construction | Construction in Progress | 5 | $1248239.39 | 2026 | PIPES | Approximately 1,848 linear feet of water mains ranging from 10 to 12 inches in diameter will be replaced and upgraded. | ||
| Morris Bridge Filter Roof Retro – COOP Site | Water | P5: Closeout | Closeout | 7 | $3975099.00 | 2024 | PIPES | The City’s existing Morris Bridge Pump Station is situated on a 56.6 acre site in Tampa, Florida, near the intersection of Bruce B. Downs Boulevard and Interstate 75. Various facilities exist on the site, including the following: Filter building, Maintenance and storage buildings, Dewatering building, ground storage tanks, electrical gear, controls, main pump station electrical rooms, and abandoned facilities that formerly served as a lime softening WTF. This project will rehabilitate and replace existing infrastructure, such as the Filter Building roof, and eliminate deteriorating facilities and equipment to increase operational and maintenance efficiency. | ||
| Lois Ave | Water | P2: Design | 90% Design Completion | 6 | $2093738.24 | 2027 | PIPES | Approximately 6,242 linear feet of water mains ranging from 2 to 6 inches in diameter will be replaced and upgraded. | ||
| 30th St (E Busch Blvd to E Bougainvillea Ave) Segment 1 (Resurfacing) | Transportation | P5: Closeout | Closeout | 7 | $3334945.60 | 2024 | Local Option Gas Tax | This project provides for complete street roadway improvements to enhance safety and multimodal connectivity, including sidewalks and trails, bicycle facilities, enhanced crosswalks, and other safety measures. Landscaping and green infrastructure components are also included. | ||
| Willow Ave WM Replacement | Water | P2: Design | 30% Design Completion | 5 | $7888229.34 | 2028 | PIPES | Approximately 17,373 linear feet of water mains ranging from 2 to 12 inches in diameter will be replaced and upgraded. | ||
| Gray Gables | Water | P2: Design | 90% Design Completion | 6 | $4969604.29 | 2027 | PIPES | The Gray Gables project will improve the City of Tampa’s water distribution system by replacing the existing water mains and increasing the capacity of the system. It will also increase capacity to serve a growing population. Approximately 12,722 Linear Feet of water mains ranging from 2 to 12 inches in diameter will be replaced and upgraded. | ||
| 7th Ave WM Replacement | Water | P2: Design | 60% Design Completion | 5 | $12609566.75 | 2030 | PIPES | Approximately 16,750 linear feet of water mains ranging from 6 to 20 inches in diameter will be replaced and upgraded. | ||
| Bayshore Blvd & Swann Ave - New Traffic Signal | Transportation | P1: Planning | Planning | 4 | $1500000.00 | 2026 | Other Agencies | This project includes design and construction of a new traffic signal to improve safety and enhance access for the community. The project includes marked crosswalks, pedestrian signals, ADA-compliant ramps, and detectable warning mats. | ||
| Downtown Phase II Collection System Rehabilitation | Wastewater | P5: Closeout | Closeout | 5 | $1600000.00 | 2023 | PIPES | This project includes the rehabilitation of approximately 34,476 linear feet of 8-inch to 24-inch diameter gravity sewers and the rehabilitation of 480 manholes. |
Was this page helpful? or
Thanks for letting us know!
Help us improve by leaving a quick comment
- Tell us what was confusing, missing or inaccurate about this page.
- We will not reply to comments, use the Page Enhancement Request below if you want a formal reply.
- Do not submit any personal or sensitive information such as account numbers or names.
- OR-
For a formal response complete the Page Enhancement Request form.